Back to 2002 Production

IDWGP April Production

IDWGP Gross Production Table
Turbine

Name

Turbine

Type

Average

W/S

(m/s)

Average

Power

(kW)

Capacity

Factor

Total

Energy

(kWHrs)

Expected

Energy

(kWHrs)

Perf.

Ratio

Online

(Hrs)

N.Rdy

(Hrs)

Avlblty

(%)

T1 Z-50 9.90 372.4 0.50 266,589 315,662 0.84 623.5 34.8 95.2
T2 Z-50 9.81 375.9 0.50 269,139 315,230 0.85 600.3 48.7 93.2
T3 Z-50 9.36 375.6 0.50 268,448 296,283 0.91 639.8 11.5 98.4
Avg.   9.69 374.6 0.50 268,059 309,058 0.87 621.2 31.7 95.6
Tot.         804,176 927,175   1,863.7 95.0  
* IDWGP Monthly Station Power Consumption
April 1st,2002 April 30th,2002 10,376

IDWGP Monthly Net Generation

April 1st,2002 thru April 30th,2002 793,800
IDWGP YTD Net Production
January 1st,2002 thru April 30th,2002 2,993,200
** IDWGP Monthly Power Consumption from Grid
April 1st,2002 thru April 30th,2002 1,400
** IDWGP YTD Power Consumption from Grid
January 1st,2002 thru April 30th,2002 5,600

* Power consumed by the Wind Farm when the Turbines are on-line and producing electricity.

** Power consumed by the Wind Farm when the Turbines are off-line. This power is feed in to the Turbines from the Grid.

Back to 2002 Production